Board Meeting – January 22, 2025 – 4:00pm
Mennies, Durand, and Winslow Schools’ renovations include conversion from 100% electric HVAC to energy efficient, Natural Gas HVAC, along with removal of all existing interior/exterior HVAC components. New ductwork, VAV’s, LED lighting, and acoustic ceilings have been installed. HVAC roof top units are being installed as they are delivered. Phase I is expected to be completed by the end of September 2022, with Phase II beginning in June 2023.
Dane Barse School’s multi-phased HVAC upgrade project is expected to begin in September of 2022 with a scheduled completion by September of 2024. This project also includes asbestos abatement in addition to complete HVAC replacement.